Case study · City of Charleston

Getting a site plan through Charleston's TRC

Nine City departments review every set of plans in Charleston. We read 1,291 Technical Review Committee cases and their comment letters to show what an applicant has to know before submitting.

Between 107 and 168 new projects a year

The City opened 1,291 TRC cases with a filing date from August 2017 to October 2026: 939 site plans and 352 subdivisions. Since 2018, between 107 and 168 cases were filed in each full year.

TRC cases filed each year, and how many of them are approved so far

Filed Approved so far

84
2017from Aug 17
168
2018
138
2019
107
2020
135
2021
130
2022
163
2023
132
2024
130
2025
92
2026to Oct 8

Cases filed in recent years are still moving through review, so their approved count is still growing.

The numbers
FiledCasesSite plansSubdivisionsApproved so far
2017 (from Aug 17)84493547
20181681214792
20191381122674
2020107763150
20211351112484
2022130993172
20231631273673
2024132933959
2025130854554
2026 (to Oct 8)9262304
No filing date held12480
Where the 1,291 cases stand today
  • 609 Approved
  • 370 Still in review
  • 24 Withdrawn
  • 6 Expired
  • 282 Status not yet readable from the portal

Every department reads the plans, and most ask for something the first time

On a first submission, the City's portal shows each department's verdict. This is how often each one asked for revisions.

First-round reviews sent back for revision, by department
Stormwater 91% 1,232 of 1,352
Engineering 85% 1,147 of 1,348
Zoning 76% 1,083 of 1,433
Traffic & Transportation 74% 1,050 of 1,413
Planning 69% 974 of 1,412
ADA 60% 844 of 1,412
Fire Marshal 57% 803 of 1,410
Parks 55% 779 of 1,415
GIS (addressing) 54% 771 of 1,415

A first submission is where the City tells the design team what its own manuals require. It is normal to go back at least once.

Approval usually takes five rounds

Of the 608 approved cases with review rounds held, the median case was approved in round 5 (middle half: round 4 to round 6). 6 were approved in one round, 24 in two, 100 in three, and 478 (79%) needed four or more.

The last round is usually the one that is approved, so a five-round case was sent back four times.

Approved cases by the round they were approved in (608 cases)
6
1
24
2
100
3
124
4
121
5median
118
6
68
7
28
8
13
9
6
10+

Round approved in

About 15 months from filing to approval

For the 597 approved cases with both dates held, the median time from filing to approval was 448 days (middle half: 260 to 711 days). Site plans: a median of 459 days (421 cases). Subdivisions: 389 days (176 cases).

The first review comes back fast: a median of 27 days from filing (middle half: 17 to 52 days; 1,165 cases). Most of the time after that is rounds of revision, by the design team and by the City.

Days from filing: the median (the mark) and the middle half of cases (the band), 0 to 800 days
First review back1,165 cases 27 days 17 to 52
Approval, all cases597 cases 448 days 260 to 711
Approval, site plans421 cases 459 days 274 to 724
Approval, subdivisions176 cases 389 days 239 to 663

A first letter carries dozens of comments

Where we hold the first-round letters (453 cases), a case's first round brought a median of 58 comment items (middle half: 23 to 104). One department's letter carried a median of 32.

Who wrote the first-round comments (19,474 items that print a department)
Stormwater 36%
Engineering 18%
Zoning 16%
Traffic & Transportation 13%
Planning 5%
Parks 5%
Fire 4%
ADA 2%
GIS 1%

About half of first comments are about the paperwork, not the design

Two people each sorted the same 200 first-round comments, picked at random, working separately from the comment's words alone. By both readings, about half asked for paperwork, and the two agreed on paperwork-or-not for 174 of the 200.

Paperwork means a label, a note, the City's project ID on the cover, a standard detail, a signature, a form, a fee, or a permit from another agency. Design means stormwater calculations, fire access, sight distance, trees or grading. The rest were information or questions.

What this means for an applicant: much of a first letter can be avoided before submitting, if the team knows the City's checklists.

The same rules come up again and again

Across the 716 cases whose comment letters we hold, these requests appear again and again.

Cases whose letters carry the request (of 716)
  1. Stormwater plan review fee: $500 plus $200 per disturbed acre 442 cases 62%
  2. Post the street address in letters at least 4 inches tall 411 cases 57%
  3. Put the City's TRC project ID on the title sheet 410 cases 57%
  4. City garbage trucks cannot back up: show they can turn around, or bins go to the street 152 cases 21%
  5. Fire department connection on the building, 20 to 100 feet from a hydrant 89 cases 12%

None of these is unreasonable. Each is easy to meet and easy to miss, if no one on the team has been through TRC before.

Following one project

A site plan for a new 20,000-square-foot multi-family building, filed in June 2019.

We chose it because it is close to the middle: approved in 5 rounds (the median is 5) and 450 days (the median is 448), with City letters held for its first four rounds.

450 days from filing to approval: the plans in City review (dark) and with the design team (light)

In City review, 166 days With the design team, 284 days

Of the 450 days, the plans were under City review for 166; the other 284 were the design team's time between rounds, 221 of them before the second submission.

Round by round, from the City's portal
RoundSubmittedReview doneDays in reviewSent back by
12019-06-032019-06-20178 of 10 reviews
22020-01-272020-04-28927 of 10 reviews
32020-06-152020-07-16315 of 10 reviews
42020-07-272020-08-13172 of 10 reviews (Stormwater, Zoning)
52020-08-172020-08-269none: approved

The City's letters number their own reviews, which do not line up with the portal's rounds, so the letters are quoted below by the City's own label.

  1. The first letters labelled “1st Review” by the City

    55 comments, from Zoning, Traffic, Parks and ADA. Some are paperwork:

    “Stop sign locations must be labeled on plans at egress onto the right-of-way.”
    “Label the 4” double yellow centerline at the ingress/egress.”

    Some are design:

    “Project requires a traffic impact study.”
    “Provide a sidewalk across the entire frontage of the project as discussed.”
    “Study and remove five parking spaces out of the TPZ as discussed.”
  2. Other boards come into it

    The letters say the project needs final Design Review Board approval before final TRC approval, and must keep the trees a zoning appeals approval required:

    “Project requires final DRB approval prior to final TRC approval.”
    “Preserve the pine trees as per the BZA-SD approval.”
  3. The second letters labelled “2nd Review”

    104 comments, 55 of them from Stormwater, among them:

    “Provide critical line boundary approval from SCDHEC.”
    “Show the location of the concrete washout area.”

    By the portal's round 4, only Stormwater and Zoning still sent it back; round 5 was approved.

Other ordinary cases we looked at
PlanRoundsDays, filing to approvalLetters held for rounds
New 20,000 sq ft multi-family building (the one followed)54501-4
New 8,500 sq ft office building44621-3
Two new buildings, 4 homes55061-4

Method and limits

Source
The City's TRC portal records (submittals, department verdicts, dates) and the City's comment letters, as read into our database: 1,291 TRC case numbers at the City of Charleston, read 2026-10-16. Every figure was measured by a saved query, run twice, with identical results.
Dates
The filing date is the date held on the case record (1,279 of 1,291 cases have one). The approval date is the completion date of the latest submittal the portal marks approved.
Rounds
Rounds are the portal's submittal versions; for a case with more than one plan sequence, the highest version is used.
Statuses
282 cases (22%) show a status we cannot yet settle from the portal's wording; they are counted neither as approved nor as not approved.
Comment letters
Held for 716 of the 1,291 cases (55%); the comment figures describe those cases only. Later letters can carry earlier comments forward with the applicant's reply, so the page counts first-round comments only.
Departments
12,383 of the 31,857 first-round comments (39%) print no department, mostly comments drawn on the plans; department shares are of the 19,474 that do.
Paperwork or design
The definition was written before counting. Two readers labelled the same 200 random first-round comments separately: 92 and 102 of the 200 were paperwork, and they gave the same answer on paperwork-or-not for 174 of the 200. So the page says “about half”, never one exact share. A word rule over all 31,857 first-round comments finds at least 28% (8,951), a floor: it misses about a third of what a person calls paperwork.
Repeated requests
A case is counted when its comments carry the request's words.

What the data could not support

  • One exact paperwork share for every comment: the best word rule agrees with a person 71 times in 100, so the page says “about half” and uses the rule only as a floor.
  • That applicants keep failing the same comments: about 12% of first-round comments come back word for word in round 2 (750 of 6,075, on 208 cases whose letters list fresh comments each round), and the ones that come back most are standing conditions that can only close at the end, such as posting the address or bringing another agency's permit once it is issued. That is the process working.
  • The department behind every comment: 39% of first-round comments print none.
  • Comment figures for all 1,291 cases: letters are held for 716.
  • Whether review got faster or slower over the years: recent years have many open cases, so a year-by-year time would mislead.
  • That the City is slow: not our claim, and not shown. The first review comes back in a median of 27 days; most of the time is rounds of revision, on both sides.

City of Charleston TRC portal records and comment letters, read 2026-10-16.